Queensland heat wave on 22 Jan 2025 caused lack of reserves LOR2 and high spot prices for 2 hrs

A Queensland scorcher on 22 Jan 2025 caused lack of reserves LOR2 and high spot prices $14,000/MWh for 2 hrs


Fig 1: Australia’s synoptic chart for 22 Jan 2025

Townsville 35ºC, Mackay 33 ºC, Mount Isa 41 ºC, Gladstone 36 ºC, Bundaberg 33 ºC, Toowoomba 34 ºC, Roma 42 ºC, Birdsville 47 ºC, Sunshine Coast 36 ºC, Brisbane 36 ºC, Gold Coast 37 ºC.

Fig 1a: NEM max temperature at 3 pm, 36 ºC average

Fig 2: AEMO market notices on lack of reserves

There was actual lack of reserve LOR1 for more than 5 hrs and LOR2 for more than 3 hrs. As a result, prices went up to $ 14,300/MWh for almost 2 hrs starting at 6 pm.

Wattclarity:
Only 400MW spare (a 4% IRPM) in the QLD-only ‘Economic Island’ on Wednesday 22nd January 2025 https://wattclarity.com.au/articles/2025/01/22jan-qld-irpm-4percent/

Fig 3: AEMO dashboard showing demand and spot prices in Queensland 22 Jan 2025

This screen shot was taken at 20:40 when prices had come down to $200/MWh after there were high prices >$14,000/MWh for almost 2 hrs.

Fig 4: Queensland generation by fuel type 22 Jan 2025

Critical time was shortly after sunset, with a maximum generation at 7 pm

Coal plants:

Fig 5: Queensland coal plants capacity and generation at 7 pm 22 Jan 2025

Gladstone #6 was offline and Tarong North had an unplanned outage, reducing available capacity from 8,119 MW to 7,396 MW (91%). Out of this capacity only 6,543 MW (88%) were actually generated at 7 pm.  High ambient temperatures reduce efficiency of heat engines.

Fig 6: Gladstone unit 2 switched offline at 19:31, 22nd January 2025

More details at WattClarity: https://wattclarity.com.au/articles/2025/01/22jan-gstone2-off/

Fig 7: Queensland coal plant generation 22 Jan 2025

About Callide we remember:
Callide C4 suffered a hydrogen explosion in May 2021, leaving half a million people without power. It took more than 3 years to repair the plant which re-opened in August 2024
https://www.abc.net.au/news/2024-06-25/qld-callide-power-station-explosion-fault-report-energy-battery/104017452

Callide C3’s cooling plant collapsed in October 2022. It took 17 months to repair and return to service in April 2024
https://www.abc.net.au/news/2022-11-01/structural-failure-at-callide-power-station-c3-unit/101602444

Major maintenance program wraps-up at Callide Power Station
20 Dec 2024
https://www.csenergy.com.au/news/major-maintenance-program-wraps-up-at-callide-power-station

Gas peaking plants:

Fig 8: Queensland gas peaking plants generation 21 – 23 Jan 2025

Fig 9: Queensland’s largest gas plant Darling Downs 21 – 23 Jan 2025

Distillate peaking plants

Fig 10: Queensland diesel plants 21 – 23 Jan 2025

A whopping 320 MW diesel power at a critical time!

Fig 11: Queensland’s largest distillate plant 21 Jan – 23 Jan 2025

All 3 units were needed.

Hydro

Fig 12: Queensland Pumped Hydro 21 – 23 Jan 2025

In 3 days, generation was 9.9 GWh with pumps requiring 9 GWh from the grid, almost balanced.

Fig 13: Queensland’s largest pumped hydro plant Jan 21 – 23 2025

Wind

Fig 14: Queensland wind generation 21-23 Jan 2025

Not much wind in the afternoon/evening. Wind ramped up when it was too late, between 8 pm and 10 pm.

Batteries

Fig 15: Queensland Batteries – Discharging and charging 21-23 Jan 2025

Over this period, charging was 2.9 GWh allowing a discharge of 2.1 GWh at exactly the time required. The largest battery is Western Downs (270 MW, 1,080 MWh)

Imports

Fig 16: Queensland imports 21-23 Jan 2025

After 2 short export bursts of 480 MW between 8:30 and 2:30 pm, Queensland needed imports (from NSW), but they dropped from 480 MW at 5:30 pm to 200 MW at 7 pm, to rebound to 600 MW by 9 pm.

Impact on NSW

Fig 17: NSW price spikes on 22 Jan 2025

There were also price spikes in NSW, at a very modest demand level 9,500 MW due to cooler air coming from the South (see location of high pressure cell in Fig 1 with winds turning ant-clockwise up the east coast).

Summary and conclusion

Queensland is absolutely dependent on coal and peaking plants using coal seam gas. The minimum coal generation capacity needed (at the time of maximum solar output) is around 4 GW. That would be the “base load” running 24 hrs/day. The Liberal opposition under Dutton has proposed 2 nuclear power plants in Queensland, one in Callide and one in Tarong. Although no capacities have been mentioned the AP-1000 reactors have 1.1 GW each.

19 June 2024

The large-scale AP-1000 reactors mentioned by Mr Dutton today have a capacity of 1.1 gigawatts (GW), and he suggested small modular reactors would have a capacity of 0.47 GW. 

https://www.abc.net.au/news/2024-06-19/dutton-reveals-seven-sites-for-proposed-nuclear-power-plants/103995310

Fig 18: Nuclear power sites proposed by the Liberal opposition

So 2 reactors for Queensland would not be enough and 1.8 GW would have to come from a combination of renewables plus storage (batteries, pumped hydro).